| 01. |
Name
of the Project |
: |
Improvement
to Gundeimura M.I.P. D/W. |
| 02. |
Name
of the Village |
: |
Gundeimura |
| 03. |
Name
of the Grampanchayat |
: |
Kantapali |
| 04. |
Name
of the Block |
: |
Barkote |
| 05. |
Name
of the District |
: |
Deogarh |
| 06. |
Assembly
Constituency |
: |
Deogarh |
| 07. |
Catchment
Area |
: |
32.50
sq..Km. |
| 08. |
Design
Ayacut |
: |
278.50
hactress Khariff
20.00 hactress Rabi |
| 09. |
Administrative
Approval Received |
: |
118.65
lakhs. vide letter no. 747 dt. 11/12/01 of C.E.O. of W.O.D.C.
Bhubaneswar. |
| 10. |
Expenditure
Incurred |
: |
95.47
lakhs upto 9/04 |
| 11. |
Date
of Commencement |
: |
02/05/2002
(Head Works) |
| 12. |
Date
of Completion |
: |
10/04/2003
(Head Works) |
| 13. |
Additional
ayacut created upto 9/04 |
: |
100
hactres in Khariff |
| |
|
|
|
| STATUS
OF WORKS |
| A. |
Head
Works |
: |
Construction
of D/W of length of 70mtrs. alongwith scouring sluice and two
nos. of head regulator (left and right) has already been completed. |
| B. |
Distribution
System |
: |
Construction
of Right main canal completed from RD 00.00 to 300mtrs. which
provides irrigation to 60 hactres during Khariff. Balance work
is under progress. Construction of left main canal completed
from RD 00m. to 560m. which provides irrigation to 40 hactres
during khariff. |