Improvement
of road from Ainthapali to Fatak Road Sambalpur from 0/854
Km to 1/460 Km under W.O.D.C.
03.
A/A
AMOUNT
:
47.49
LAKHS
04.
AMOUNT
DEPOSITED BY WODC
:
40.00
LAKHS
05.
DATE
OF COMMENCEMENT
:
30/12/2003
06.
DATE
OF COMPLETION
:
29/10/2004
07.
PRESENT
PHYSICAL PROGRESS
:
Work
Completed
08.
DETAILS
OF WORK
:
Improvement
of road (4 leaning) by raising through sand filling, crusher
dust, metalling 3 years, surface dressing, Sealcoating median
with grill at road center.