Home
 
CONSTRUCTION OF H.P.V.C. AT 6TH K.M. ON
MANGASPUR DARLIPALI ROAD
 
   
 
01. Name of Work : Construction of approach road to Kansbahal Dam Project for the year- 2003-04 (Such as M2, PMC, SC from 5/80 Km. - 6/78 Km. M1, M2, PMC, SC from 6/78 Km. to 7/18 Km.)
02. Estimated Cost :
Rs. 9,73,000/-
03. Date of completion : 22/05/2004
 
The total length of the approach road was 7.18 Km. which starts at Rly. level crossing near Kansbahal & ends at Kansbahal Irrigation Project Colony. This road also connected Rajgangpur civil Sub-divn. This road passes through enterior tribal village like Kansbahal, Panposh, Kadambahal etc. The road has been impoved with BT from 0/0 Km. to 5/0 Km., Moonum sub-base from 5/0 Km. to 5/40 Km. and rest portion was earthen. The entire people of this area were depending on this road for their medical facilities, educational facilities and transportation of their agricultural products to their nearest market i.e. Rajgangpur. During the heavy rain during last years the old road surface from 5/80 Km. to 7/18 Km. has been fully damaged. The people as well as the political representatives of this area were pressing hard for improvement of this road.

This estimate had been framed, Administrative Approval obtained and work completed in due course out of WODC assistance during year 2003-04.
 
Home